Bridge Repair/Rehabilitation Project: State Road (SR) 5/US 1/Overseas Highway/Old Seven Mile Bridge from Knights Key to Pigeon Key (MM 46.8 to MM 44.6)
Project Start: September 2017

Estimated Projected Completion: July 2021
PLANNED CONSTRUCTION ACTIVITY: The Contractor will be performing abrasive blasting and steel repair work under the bridge this week. However, as a reminder: Please note that there are ten parking spaces and two pavilions open to the public, but the bridge and underpass will remain closed for the duration of the project.